What acronym refers to the influence of procurement considerations at the design stage for product configurations?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the ASU SCM355 Supply Management Exam 1 with practice quizzes. Test your knowledge with flashcards and multiple choice questions, complete with detailed explanations. Master your exam!

The correct acronym that refers to the influence of procurement considerations at the design stage for product configurations is DFM, which stands for Design for Manufacturing. This concept emphasizes the importance of considering manufacturing capabilities and procurement requirements during the design phase of a product. It helps ensure that products are designed with both cost-effectiveness and manufacturability in mind, ultimately facilitating a smoother production process and reducing potential supply chain issues.

When designers incorporate DFM principles, they are better able to select materials, processes, and methods that align with capabilities of suppliers and the overall supply chain strategy. This proactive approach can lead to improved quality, reduced waste, and streamlined production processes.

The other options, while related to design and manufacturing considerations, do not specifically focus on the procurement influence during the design stage. Hence, the focus of DFM on integrating procurement insights with product design clearly sets it apart as the most relevant acronym for this scenario.